how long does it take before you remove the forms and scaffoldings of a roof deck concrete slab? ito po ba yung sabing curing period?

Alaska survived a late-game rally by Ginebra to win 104-90, leading the series at 2-0 and now one win away from the title.
read more
The ADMU Lady Eagles overpowered UST in 4 sets, ousting the Golden Tigresses and advancing to the V-League finals
read more
Guess the theme! Have you seen Twilight, Sister Act and these other movies? Share your thoughts and reviews in here!
read more
Visually breath-taking and action-packed, Star Trek: Into Darkness will please casual and hardcore fans alike.
read morehow long does it take before you remove the forms and scaffoldings of a roof deck concrete slab? ito po ba yung sabing curing period?
Our contractor set the curing period at 14 days. But if you use ready-mix 7 days would be enough.
Ah ok, Thanks. Actually my contractor removed the forms and scaffoldings just after 10 days. They used concrete mixer only, 1:2:3 concrete mixture. Worried lang akot im expecting more than 14 days to 1 mo. curing period. Ok lang *** yun baka di maattain maximum strength nung concrete?
definitely hindi naabot yung maximum (concrete mix design) strength, kasi concrete needs 28days to attain that.
depende na lang sa contractor (engineer) mo since roof deck na yan, na-determine na niya siguro na yung concrete ay nag-attain na ng enough strength dun sa 10days para pwede na tanggalin yung forms and scaffoldings (or baka hindi mo napansin na may naiwan pa na shoring yun deck mo?). baka lang din hindi mo nakita na naglagay siya ng accelerator (admixture)?
ilang floors ba yang bahay mo?
kailangan din ng water proofing?
Ive talked to my contractor, 1-2 weeks daw pde na tanggalin mga porma ng slab but still no work to be done nor put load on top of it coz still under curing period which is about 28days.There was no added accelerator (admixture) only liquid sahara for waterproofing.
As anticipated ok lang daw and no need to worry.
Ok lang ba talaga ito mga Sirs? I thought curing period is 14-28 days without removing the forms and scaffolding. and by the way, theres no shoring jack or other support left, totally bare na yung roof deck ko. Sana nga walang aberya roof deck ko.
koda, i would anticipate na nasa curing stage pa now since *** ak nbasa kung kelan ang pouring date.
normally, an inspector will look for signs of settlement. & yes, dapat po professional para hindi misleading ang facts at hindi na ma-extend ang worry period mo.
suggestion lang po ito ah. this is just one of the appropriate action sa ganyang situation.
sana po mktulong.
halos araw araw pinapacheck ko sa uncle ko yung roofdeck and so far ok naman daw. kaso nga lang di naman yun expert/professional sa ganung bagay. buti pa nga siguro pa check ko sa building inspector samin lalot wala nga kasi ko sa site at ng sa ganun wala na worries. thanks, sir quality101.
Ang alam ko yung curing period ay dapat more than 15 days para maging intact talaga *** roof deck. Ano po pinakamagandang water sealant ngayon sa market?
Yun curing period is more than 15 days- up to 28 days nga kung gusto mo talagang optimum setting. Ang sinasabi lang nila, you don't always have to wait 28 days to remove the forms and scaffoldings. Depende yan on several things. If its a large, expansive deck with sparse columns underneath, it would be more prudent to wait 28days. Kasi baka mag-sag sya under its own weight. Kung hindi naman malawak at well reinforced by rebar/matting, etc then maybe it can support itself without the forms and scaffolding as early as 15days.
for me, 20 consecutive days of no rain is enough.